Saturday, April 25, 2015

Friday, March 27, 2015

Well pump installed

Had the well pump installed yesterday.  


The front porch has had the siding finished up.  Chimney still needs finished.
 



Thursday, March 12, 2015

We have water!

The well was dug yesterday.

155 foot deep
35 g.p.m.
5" casing

Pump should be installed in a week. 







Saturday, March 7, 2015

Power poles set

Big day to finally see the power poles set.  With a week of 50-60 degree days and no rain, we expect a lot of progress to be made. 





Monday, February 23, 2015

Siding has started

Ended up being very muddy for the guys but siding has started as well as electrical rough-in.  


Tuesday, February 17, 2015

House update

Windows and the fireplace are in.  It also looks like Digger Jim put in the septic tank and leach field.